Electrical crew and material-pack estimating worksheet

Free from Relay, no signup. Defaults and sources checked November 13, 2026.

Cost a repeated scope you have already inspected and specified. Enter lead and helper hours separately, then budget one repeated material item by supplier pack. All starting numbers are illustrative, not suggested labor times, wages or prices.

Method

For each crew role: person-hours = work points × person-hours per point + whole-job setup hours; labor cost = person-hours × loaded hourly cost. Installed material units = points × units per point. Packs to buy = round up ((installed units + requested spares) ÷ units per pack). Purchase cost = whole packs × pack price. Installed material cost = installed units × pack price ÷ units per pack. Budget = crew cost + the selected material cost basis + other job costs and allocated overhead. Price = budget ÷ (1 - target margin ÷ 100); card fees and tax are excluded. Person-hours are effort, not elapsed job duration.

Worked example

Eight points at 0.5 lead hours and 0.25 helper hours each, plus 1 lead setup hour and 0.5 helper setup hour, need 5 lead and 2.5 helper person-hours. At illustrative loaded costs of $60 and $35, crew cost is $387.50. Two material units per point means 16 installed units. With 2 requested spares and 10 units per $24 pack, buy 2 packs for $48: 16 units installed, 2 requested spares and 2 additional units from pack rounding. Installed material cost is $38.40. Add $100 for other job costs and allocated overhead: the installed-unit budget is $525.90; the full-purchase budget is $535.50. At a 20% margin on entered costs before card fees, prices are $657.38 and $669.38 respectively.

What this calculation covers

An internal estimating worksheet, not an electrical design or a binding quote. No scope selection, circuit capacity, wire size, breaker choice, permit eligibility or license supervision decision is made. Lead and helper labels do not authorize a person to perform work. Quantities cover one repeated material item; list the remaining materials separately. Enter loaded costs that already include the payroll burden you intend to recover. Include missing company overhead in the job-cost allowance. Profit is calculated only on the entered costs; tax and card fees are excluded. Do not count payroll burden or overhead twice. Reports include private cost inputs; review before sharing. No stock is reserved, ordered or deducted.

Method references

  • BLS: compensation includes wages and benefits
  • SBA: separate costs and pricing assumptions
  • University of Maine: margin and markup are different

Continue your work

  • Work a crew and material takeoff example
  • Add overhead and your target margin
  • Build the customer proposal
  • Keep a separate truck parts list

Questions

Can I share the calculation with a customer?

The cost worksheet includes private labor and material costs. Keep it for your own records. Use the price handoff to prepare a separate customer estimate; tax, credits and prior payments are not recorded automatically.

All electrical resources

Related guide: Electrical crew and material takeoff.

Book a demo

All free tools

Product

  • All features
  • AI Front Office
  • Business Phone
  • Website
  • Booking
  • Pipelines
  • Scheduling & dispatch
  • Mobile App
  • Pricebook
  • Inventory
  • Time tracking & timesheets
  • Estimates & proposals
  • Invoicing & payments
  • Customer management
  • Maintenance plans
  • Review requests
  • Customer campaigns
  • Reports & profitability

Compare

  • Relay vs Housecall Pro
  • Relay vs Jobber
  • Relay vs ServiceTitan
  • Relay vs Workiz
  • Relay vs FieldPulse

Industries

  • HVAC
  • Plumbing
  • Electrical
  • Garage door
  • Appliance repair

Legal

  • Privacy
  • Terms
  • SMS Policy
  • Account Deletion

Company

  • About
  • Guides
  • Free tools
  • Help center
  • Contact
  • Support
© 2026 Relay Ops, Inc.